Hermes Airports began night-time construction works on 27–28 November for the second phase of Paphos International Airport’s long-planned upgrade. The €220 million package will install two rapid-exit taxiways, extend the southern parallel taxiway and enlarge the terminal by one-third. Once complete in mid-2027 the project is expected to raise peak-hour aircraft movements from 12 to 18 and overall passenger throughput by about 30 %.
The air-side works are timed so that flight operations continue uninterrupted; crews enter the runway after the last departure at 23:30 and hand the pavement back before the first arrival at 06:00. Hermes says the rapid-exit taxiways alone will cut average runway occupancy by 45 seconds per jet, creating new slots for both low-cost carriers and corporate aviation.
Inside the terminal, plans call for six additional departure gates, an enlarged immigration hall wired for future biometric e-gates, and a bigger baggage-handling system compatible with EU Entry/Exit System specifications. Project managers are coordinating with airlines and ground-handlers to minimise disruption, although one arrivals-level traffic lane is closed—passengers should allow an extra 15 minutes for drop-off.
For global-mobility teams the expansion promises greater seat availability on Western European and Gulf routes that routinely operate at load factors above 90 % in summer. The Cypriot Chamber of Commerce predicts the added capacity will boost winter tourism and support the island’s drive to attract regional headquarters and remote-working talent.
Hermes notes that the works dovetail with Cyprus’ ambition to join Schengen later this decade; the new immigration hall will feature automated border-control lanes that can be switched on once accession becomes reality.
The air-side works are timed so that flight operations continue uninterrupted; crews enter the runway after the last departure at 23:30 and hand the pavement back before the first arrival at 06:00. Hermes says the rapid-exit taxiways alone will cut average runway occupancy by 45 seconds per jet, creating new slots for both low-cost carriers and corporate aviation.
Inside the terminal, plans call for six additional departure gates, an enlarged immigration hall wired for future biometric e-gates, and a bigger baggage-handling system compatible with EU Entry/Exit System specifications. Project managers are coordinating with airlines and ground-handlers to minimise disruption, although one arrivals-level traffic lane is closed—passengers should allow an extra 15 minutes for drop-off.
For global-mobility teams the expansion promises greater seat availability on Western European and Gulf routes that routinely operate at load factors above 90 % in summer. The Cypriot Chamber of Commerce predicts the added capacity will boost winter tourism and support the island’s drive to attract regional headquarters and remote-working talent.
Hermes notes that the works dovetail with Cyprus’ ambition to join Schengen later this decade; the new immigration hall will feature automated border-control lanes that can be switched on once accession becomes reality.
Source: VisaHQ Global Mobility News
How VisaHQ can help
VisaHQ simplifies the visa application process for individuals and businesses. Check current travel requirements, prepare the required documents and manage your application online through the VisaHQ Cyprus portal.More From Cyprus
View all
Cyprus adopts EU Tourism Agenda 2030, pledging greener, tech-enabled visitor economy
Wizz Air operates charity ‘Wings of Hope’ flight from Larnaca to London, blending CSR with leisure travel